Restoration of Sprinklers and Public Bathrooms

bathroom1We continue to make progress on assessing renovation costs. Project Manager, Gary O’Connor, met today with the sprinkler company folks to do an assessment of the sprinkler system throughout the Roseboro. Most all of it needs to be replaced at some point. They need to do pressure tests and backwash procedures before they can complete their full assessment.

Gary is also drawing up plans to remodel the bathrooms off the lobby. We plan to keep the 1930’s urinals but need to bring the restrooms up to code. We want to put in nicer, larger stalls with full length doors and updated fixtures. This is one of the first steps in the renovation project before we will open the restaurant.